Cambodia Securities Exchange building

[Disclosure] Fourth quarterly report of PESTECH (Cambodia) Plc. in 2026 (Unofficial Translation)

Disclosure Details

Company NamePestech (Cambodia) Plc. (PEPC)
Date19 November 2026

For the 4th Quarter Ended 30 September 2026, the total revenue of PEPC was recorded at KHR 6,431 million, representing a decrease of KHR 17,979 million (≈ 74%) as compared to the corresponding quarter of FY2025 which was recorded at KHR 24,410 million. The decline is primarily due to lower contribution from the Tatay project, which reached 100% full construction completion in June 2026, and substantial completion of the Phnom Penh City Underground Distribution Project.

As of 30 September 2026, total assets were KHR 786,390 million and total liabilities were KHR 922,241 million, with equity/capital deficiency of KHR (135,851) million. (Comparative in the year 2025, assets were KHR 893,347 million and liabilities KHR 996,480 million, with equity/capital deficiency at KHR (103,133) million).

Key Performance Indicators – Q4 FY2026

• Current Ratio: 1.11 times

• Quick Ratio: 1.08 times

• Return on Assets (ROA): (0.69%)

• Return on Equity (ROE): (3.99%)

• Operating Loss: KHR (1,401) million

• Loss Before Tax: KHR (5,113) million

• Loss After Tax: KHR (5,418) million

• Total Comprehensive Loss: KHR (5,961) million

Note on Project Progress: As of this report, the construction of the 230kV transmission line from Stung Tatay Hydropower Plant to Phnom Penh is 100% complete (with the Commercial Operation Date (COD) officially declared on 15 June 2026), and the Phnom Penh City Underground Distribution Project, Phase 2 has been fully completed.

Attachments

Source: Cambodia Securities Exchange (CSX) — csx.com.kh